The expressway starts at La Son intersection (Loc Son commune, Phu Loc district, Thua Thien Hue province) and ends at Tuy Loan (Hoa Vang district, Da Nang city).
Construction began in 2015 on the 77-km-long, 22-meter-wide, four-lane highway, with a total investment of nearly 11,500 billion VND, and was expected to be completed in 2018. However, due to land acquisition issues and heavy rainfall, construction has been delayed.
The highway has over 11 km that runs through Bach Ma National Park (Hue).
An overpass crosses the valley in the Bach Ma National Park area.
The entire highway has 36 bridges where lane markings are being done and signage is being installed.
The highway has over 11 km that runs through Bach Ma National Park. Many hilly and tree-covered areas in this region have been cleared for construction.
Due to recent heavy rains, some embankments in the Bach Ma National Park area (Hue) have collapsed.
The expressway section running through Nam Dong and Phu Loc districts (Hue province) has been basically completed.
The access road to the Mui Trau tunnel is located on the La Son - Tuy Loan expressway.
In June 2020, the Ho Chi Minh Highway Management Board is expected to invite the Fire Prevention and Fighting Department to evaluate the design and construction techniques of the Mui Trau tunnel section on the La Son - Tuy Loan expressway.

Mr. Nguyen Minh Khanh, Deputy Head of Project Management Department 4 (Ho Chi Minh Highway Management Board), said that the unit has completed the installation of road signs on the expressway. "If the repair of the landslide areas proceeds smoothly, the La Son - Tuy Loan expressway could be opened for technical traffic from km 0 to km 66 in June," Mr. Khanh said.